Estimate a migration business case after inventorying dependencies and validating a target architecture. Server count alone cannot determine compatibility, effort, provider pricing or duration.
- Labor =
(planning + migration/compatibility + testing + training hours) × hourly cost. - One-off subtotal = labor + distinct other costs + additional parallel-running costs.
- Transition investment = subtotal ×
(1 + contingency percentage / 100). - Recurring monthly saving = current all-in monthly cost − proposed all-in monthly cost.
- Current horizon cost = comparison months × current monthly cost.
- Proposed horizon cost = investment + comparison months × proposed monthly cost.
- Net horizon saving = current horizon cost − proposed horizon cost.
- Simple payback = investment / positive monthly saving. With zero or negative monthly saving there is no recurring-cost payback.
- Horizon return on transition cost = net horizon saving / positive investment × 100. With zero investment this ratio is undefined.
Months start after cutover. Add only the incremental overlap spending during transition, not current spending already included elsewhere. Both recurring estimates must include comparable licensing, support, labor, data transfer and backup requirements. Retained assets, taxes, financing, discounting, growth, phased benefit delivery and outage risk are excluded unless consistently included in your inputs. Zero contingency is the starting assumption, not advice to omit uncertainty.
Reproducible example
The example uses 10 planning + 40 migration + 20 testing + 10 training hours at €50/hour, €500 other one-off spending, €500 overlap and a user-assumed 20% contingency. Investment is (80 × 50 + 500 + 500) × 1.2 = €6,000.
Current cost €1,000/month and proposed €700/month yield €300/month saving. At 60 post-cutover months, totals are €60,000 and €48,000. Net saving is €12,000, simple payback 20 months, and horizon return 200%. These values demonstrate arithmetic, not a quote or recommendation to migrate.
Sources
FinOps Foundation planning and estimating and unit economics support scoped, documented cost and value models. They do not supply the example prices or validate this calculator. AWS migration business case guidance describes the need to build a business case from an assessed workload estate.
Method and factual claims reviewed 16 October 2026. Sources support the principles described, not example inputs, price quotes or outcome predictions.